A builder rings with a big job. Starting in three weeks. Do you say yes? Most small shops answer that with a gut feel and a look at the whiteboard, and find out six weeks later that they've promised two kitchens and a vanity run for the same fortnight.
Capacity planning sounds like something for factories. It isn't. Here's a simple version that works for a crew of two to ten.
1. Know your hours available
For each week ahead, add up the hours your crew can actually work on jobs. Start with their normal hours, then take off booked leave, public holidays, TAFE days and the time you know goes to non-job work. That last part is the same number you need for working out your hourly rate, so you only have to find it once.
2. Know your hours booked, by stage
Every job you've won has hours in it: drafting, machining, edging, assembly and install. If your quotes are built from labour time standards, you already know them. Put those hours into the weeks they'll happen in.
Splitting by stage matters. You might have plenty of total hours but only one person who does the drawings, or one CNC. When drafting or machining is full, everything behind it waits.
3. Don't forget work won but not yet booked
Jobs you've said yes to but haven't scheduled are the ones that cause the crunch. Count their hours too, even if you don't know the exact week yet.
4. Compare, then decide
Booked hours against hours available, week by week, tells you straight away whether the builder's job fits, needs a later start, or needs overtime or a casual. It also shows the quiet weeks coming, early enough to chase work to fill them. Steady work is good for cash flow; feast and famine isn't.
5. Book people and machines, not just jobs
A schedule that says "Smith kitchen: week of the 20th" isn't enough. Put names and machines against the work, so you can see who's double-booked before Monday morning, not on it.
Quoted lead times you can keep
Once you can see capacity, you can quote honest lead times. Clients forgive "eight weeks" far more easily than "four weeks" that turns into ten. If the schedule still lives on a whiteboard or spreadsheet, read the signs you've outgrown it.